Mostrar 3 resultados

Descrição arquivística
Thomas Meacock fonds
Previsualizar a impressão Ver:

Thomas Meacock fonds

  • F 807
  • Arquivo
  • 1961

This fonds contains the following files:

F 807.01- Blueprints: Howard Kerr Hall - Unit III, 1961.

F 807.02 - General Trades: Contract Requirements for Fixed Sum Contract - Howard Kerr Hall - Unit III, 1961.

Meacock, Thomas

Howard Kerr Hall - Unit III blueprints

The file consists of a set of 115 blueprints (numbered 44) for Unit III of Howard Kerr Hall. Notations on the drawings include, among others : Burwell R. Coon, Architect ; Prov. Ont. Dept. of Public Works ; D.G. Creba - Chief Architect ; J.D. Millar - Deputy Minister.

The drawings are divided and numbered according to 5 categories : architectural (34), structural (21), heating and ventilation (14), plumbing (15) and electrical (31).
Plans are as follows:

Architectural (33 drawings) :

    1. Site Plan And Borings
    1. Plot Plan
    1. Basement & Swimming Pool Part "A"
    1. Ground Floor Plan Part "A"
    1. First Floor Plan Part "A"
    1. Second Floor Plan Part "A"
    1. Third Floor Plan Part "A"
    1. Basement Plan & Details Part "B"
    1. Ground Floor Plan Part "B"
    1. First Floor Plan Part "B"
    1. Second Floor Plan Part "B"
    1. Third Floor & Penthouse Plans Part "B"
    1. Basement Plan Details Part "C"
    1. Ground Floor Plan Part "C"
    1. First Floor Plan Part "C"
    1. Second Floor Plan Part "C"
    1. Third Floor Plan Part "C"
    1. Roof Plan And Details
    1. Gerrard St. Elev.; Section Through Cafeteria & Gym; North Elev. From Courtyard
    1. Victoria Street Elevation: Section Through Portico CC-55
    1. Elev. From Court Looking West/Section Through Porticos CC-55 & A108
    1. Gould St. Elev; South Elev. From Court; East Elev. Of Portico CC-1 & A108/ North Elev. Of Porticos CC-1 & CC-55
    1. Longitudinal Sections
      Longitudinal Sections :
    1. Sections #1 To #6 #9 #11
    1. Sections #12 #13
    1. Sections #14 #15 #16 #17
    1. Typical Corridor Sections /Section #10 /Section #15
    1. Stage & Proscenium /Sections #18 & #19
    1. Section #20 /Stair #1
    1. Section #21 /Stair #5
    1. Section #22 /Stair #11
    1. Section #7 /Stair #13
    1. Section #8 /Stair #14

Structural (22 drawings) :

  • S1 Foundation Plan
  • S1A Foundation Section "A"
  • S2 Ground Floor Framing Plan "A"
  • S3 First Floor Framing Plan "A"
  • S4 Second Floor Framing Plan "A"
  • S5 Third Floor Framing Plan "A"
  • S6 Roof Framing Plan "A"
  • S7 Column Schedule "A"
  • S8 Foundation Plan "B"
  • S9 Ground Floor Framing Plan "B"
  • S10 First Floor Framing Plan "B"
  • S11 Second Floor Framing Plan "B"
  • S12 Third Floor Framing Plan "B"
  • S13 Roof Framing Plan "B"
  • S14 Column Schedule Part "B"
  • S15 Foundation Plan "C"
  • S16 Ground Floor Framing Plan "C"
  • S17 First Floor Framing Plan "C"
  • S18 Second Floor framing Plan "C"
  • S19 Third Floor Framing Plan "C"
  • S20 Roof Framing Plan "C"
  • S21 Column Schedule "C"

    Heating & Ventilation (14 drawings) :

  • H1 Basement Floor Plan & Low Level Of Swimming Pool Part "A"
  • H2 Ground Floor Plan Part "A"
  • H3 First Floor Plan Part "A"
  • H4 Second Floor Plan Part "A"
  • H5 Third Floor; Heating & Ventilation RM. Floor Plan Part "A"
  • H6 Basement & Ground Floor Plans Part "B"
  • H7 First & Second Floor Plans Part "B"
  • H8 Third Floor & Penthouse Floor Plan Part "B"
  • H9 Basement Floor Plan Part "C"
  • H10 Ground Floor Plan Part "C"
  • H11 First Floor Plan Part "C"
  • H12 Second Floor Plan Part "C"
  • H13 Third Floor Plan Part "C"
  • H14 Roof Plan & Details

Plumbing (15 drawings) :

  • P1 Basement & Details Part "A"
  • P2 Ground Floor & Details Part "A"
  • P3 First Floor & Risers Part "A"
  • P4 Second Floor & Risers Part "A"
  • P5 Third Floor & Schedule Part "A"
  • P6 Basement & Plot Plans Part "B"
  • P7 Ground Floor & Risers Part "B"
  • P8 First Floor & Details Part "B"
  • P9 Second Floor & Details Part "B"
  • P10 Third Floor & Penthouse Part "B"
  • P11 Basement & Details Part "C"
  • P12 Ground Floor & Schedule Part "C"
  • P13 First Floor & Risers Part "C"
  • P14 Second Floor & Risers Part "C"
  • P15 Third Floor & Risers Part "C"

Electrical (31 drawings) :

  • E1 Plot Plans & Symbols
  • E2 Panel Riser & Details
  • E3 Basement Lighting Part "A"
  • E4 Ground Floor Lighting Part "A"
  • E5 First Floor Lighting Part "A"
  • E6 Second Floor Lighting Part "A"
  • E7 Third Floor Lighting part "A"
  • E8 Basement Power Part "A"
  • E9 Ground Floor Power Part "A"
  • E10 First Floor Power Part "A"
  • E11 Second Floor Power Part "A"
  • E12 Third Floor Power part "A"
  • E13 Basement Lighting & Power Part "B"
  • E14 Ground Floor Lighting Part "B"
  • E15 First Floor Lighting Part "B"
  • E16 Second Floor Lighting Part "B"
  • E17 Third Floor Lighting Part "B"
  • E18 Ground Floor Power Part "B"
  • E19 First Floor Power Part "B"
  • E20 Second Floor Power Part "B"
  • E21 Third Floor Power Part "B"
  • E22 Basement Lighting & Power Part "C"
  • E23 Ground Floor Lighting Part "C"
  • E24 First Floor Lighting Part "C"
  • E25 Second Floor Lighting Part "C"
  • E26 Third Floor Lighting part "C"
  • E27 Ground Floor Power Part "C"
  • E28 First Floor Power Part "C"
  • E29 Second Floor Power Part "C"
  • E30 Third Floor Power Part "C"
  • E31 Stage Lighting

General Trades: Contract Requirements for Fixed Sum Contract - Howard Kerr Hall - Unit III

This document relates to the construction of Unit III of Howard Kerr Hall. Unit III is Kerr Hall South, from the corner of Church and Gould to the corner of Gould and Victoria. The document is numbered Set No. 21 and contains the following sections :

  • General Contract Form
  • General Instructions and Requirements
  • General Trades Index
  • Specifications (by trade/material/function)
  • Sub-Tender List
  • Tender Form